UGI System Upgrades Set to Begin in Harrisburg on May 28

UGI Utilities, Inc. is scheduled to start a gas main replacement project in Harrisburg on May 28. The work is part of UGI’s commitment to provide safe and reliable service and will impact the following streets:

  • Emerald Street between North 4th Street and North 3rd Street
  • Orange Street from Emerald Street
  • Logan Street between Emerald Street and Woodbine Street
  • Woodbine Street between Logan Street and North 3rd Street
  • North 3rd Street between Woodbine Street and Maclay Street
  • Maclay Street between North 3rd Street and North 2nd Street

Construction is scheduled for Monday through Friday, between the hours of 7am and 5pm. Drivers, residents, and business owners may experience road closures, detours, and traffic delays during construction hours. Parking will be restricted on the impacted streets during these hours. There will be some interruptions to natural gas service. This will require UGI to have access to properties to inspect and relight equipment.

Construction is scheduled to be completed by mid-September. Weather and working conditions may impact the completion date.

UGI’s gas main replacement projects also provide an opportunity for some homes and businesses within the project areas to convert to natural gas. UGI encourages anyone along project routes to contact the company at 800-276-2722 or gasconversion@ugi.com if they are interested in converting.