UGI to Continue System Upgrades with Work Planned for Allentown Starting March 1

UGI Utilities, Inc. is scheduled to begin gas main replacement projects on March 1 along several streets in Allentown. The work is part of UGI’s commitment to provide safe and reliable service and will impact the following streets:

·      Wyoming Street between South 12th Street and Lehigh Street

·      South 12th Street between Colorado Street and West Cumberland Street  

·      South 11th Street between Wyoming Street and West Cumberland Street 

·      South Howard Street between Wyoming Street and Hoe Street 

·      Hoe Street between South Howard Street and Wyoming Street 

Construction is scheduled for Monday through Friday, between the hours of 7am and 5pm. Drivers, residents, and business owners may experience road closures, detours, and traffic delays during construction hours. Parking will be restricted on the impacted streets during these hours. There will be some interruptions to natural gas service. This will require UGI to have access to properties to inspect and relight equipment.

Construction is scheduled to be completed by late June. Weather and working conditions may impact completion date.

UGI Utilities, Inc. is a natural gas and electric utility company that serves more than 740,000 customers. Additional information about UGI Utilities, Inc. is available at www.ugi.com

 